Friday, October 16, 2015

14 Fairway Bunker Renovation


Camera roll from start to finish of the work performed by the Grounds Departmemt to enhance the playability of #14 fairway bunkers.



Beginning stages of sod removal & planning overall design


Reshaping the bunker to provide a modernized look & improved playability


Removal of old sand on the left side fairway bunker


Reshaping and drainage completed on the right side fairway bunker


Reshaping of left side fairway bunker


Bunker liner being installed 


Liner & final grading complete


Installing the new bunker sand


Installing drainage on left side bunker


Drainage complete


Finishing up the final grade


Sod work complete and finished product looking very nice


Sodding the area where we performed bunker removal


Left side fairway bunker complete 👍🏻👍🏻


Hole #14 fairway bunker work complete and looking outstanding 

Being an In-House project the entire process took 3 weeks to complete while also maintaining the course.  Renovation work is very rewarding for myself and the members of the Grounds Department that were heavily involved and a big thanks goes to Andrew & the guys for a job well done.